SoftBank Group

Procurement plans revised at Q2 end; loss recognized for the six months ended 30 September 2026

Read the evidence, what it covers and what is still unclear.

Read the source-linked updates or inspect technology notes.

Later research and source checks

Supplementary notes can update existing programs or describe adjacent work. They are not extra adoption counts.

SoftBank records a $3.73bn loss after revising AI data-center power-equipment procurement

SoftBank reports a $3.73bn loss on US AI data-center power-equipment procurement: $2.85bn in non-refundable advances and $0.88bn in contract modifications and settlements.

Up to $2.1bn in rebates depends on future equipment purchases over ten years. The rights were not recognized as an asset; they are not realized recovery or an offset to the reported loss.

Limits: These are issuer-reported accounting figures, not independent project verification. Potential rebates require future purchases and cannot be deducted as recovered cash. Original materials do not establish a supplier-specific loss, 13 GW of cancellations, default, cancellation of all associated campuses or a collapse in gas demand. The Q&A uses 10 November materials; revised presentations and the 12 November slide govern later updates. No oilfield AI failure or project net ROI is inferred.

SoftBank Group — Consolidated Financial Report, six months ended 30 September 2026 · 2026-11-10

SoftBank Group — Q2 FY2026 Investor Briefing Q&A · 2026-11-10

SoftBank Group — Updated slide: Equipment for U.S. AI Data Center (3) · 2026-11-12